Decommissioning Activities
Recording of operational values during run-down:
- Shaft vibrations
- Absolute and differential expansions Eccentricity
- Turbine shaft position
- White metal bearing temperatures Bearing oil pressures
- Run-down time from barring
Disassembly Activities
High-Pressure (HP&IP) Turbine
- Removal of instrumentation (e.g., diff & absolute expansion probes, thermocouples).
- Marking of valve reference positions.
- Measuring of turbine cold datum sizes.
- Bolt heating and removal of the top outer and inner casings.
- Removal of diaphragms, gland carriers, and rotors.
- Measuring and measuring of shaft axial and radial clearances.
- Removal of the bottom and top half components.
Low-Pressure (LP) Turbine
- Removal of cross-over pipes, gland boxes, and exhaust hoods.
- Removal of the top and bottom inner casings.
- Dismantling and removal of diaphragms and diaphragm carriers.
- Removal of LP rotors.
Centerline Work
- Removal of pedestal instrumentation.
- Opening and removal of coupling guards and pedestal covers.
- Removal of top and bottom half bearings and oil baffles.
- Measuring and recording of rotor running positions.
- Recording of shaft concentricity and alignment.
- Splitting of coupling.
Turbine Valves (Emergency Stop Valves (ESV), Control Valves (CV) and LP/IP Bypass)
- Recording of stroke checks.
- Removal of servo couplings, heat shields and oil pipes.
- Removal and recording of servo motor pretension.
- Stripping of valve internals.
Servo Motors
- Stripping of servo motors for inspection.
- Removal of power and control blocks.
- Removal of Moog control valves.
- Removal of power pistons and spindles.